Washington Hall Playground Basketball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts at Washington Hall Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
October 2019
Procurement
Start Date: October 2019
Projected Completion Date:
July 2020
Completion
Date:
May 2022
Construction
Start Date: September 2022
Projected Completion Date:
September 2023
Completion Date: February 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Washington Hall Park, Brooklyn
Washington Avenue, Park Avenue, Hall Street
Community Board: 02
Project Staff
Project Liaison: Davey Ives