Cadman Plaza Park Oval Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the oval at Cadman Plaza Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: April 2021
Completion Date: October 2022

Construction

Start Date: January 2023
Projected Completion Date: January 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $6,399,000
Funding Source: Mayoral

Location

Cadman Plaza Park, Brooklyn
Between Cadman Plaza East, Cadman Plaza West, the Brooklyn Bridge, and the Brooklyn War Memorial
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025