McCarren Park Ballfield 3 Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Ballfields 1, 2 and 3 in McCarren Park

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: March 2024

Procurement

Start Date: March 2024
Projected Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

McCarren Park, Brooklyn
Lorimer Street, Driggs Avenue, North 12th Street and Bedford Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024