Yellowstone Park Fencing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fencing at Yellowstone Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020
Completion Date: October 2022

Construction

Start Date: April 2023
Projected Completion Date: January 2024
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $262,000
Funding Source: City Council

Location

Yellowstone Park, Queens
68th Avenue, 68th Road, 108th Street, Yellowstone Boulevard
Community Board: 06

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024