Coney Island Boardwalk Security Measures Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct bollards and other security measures at entrances to Coney Island Boardwalk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: November 2022

Construction

Start Date: May 2023
Projected Completion Date: April 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $5,150,000
Funding Source: Mayoral

Location

Coney Island Beach & Boardwalk, Brooklyn
Brighton 15th Street to West 37th Street
Community Board: 13, 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project