Coney Island Boardwalk Security Measures Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct bollards and other security measures at entrances to Coney Island Boardwalk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date:
July 2020
Procurement
Start Date: July 2020
Projected Completion Date:
March 2021
Completion
Date:
November 2022
Construction
Start Date: May 2023
Projected Completion Date:
April 2024
Completion Date: April 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Coney Island Beach & Boardwalk, Brooklyn
Brighton 15th Street to West 37th Street
Community Board: 13, 15
Project Staff
Project Liaison: Davey Ives