Carl Schurz Park Security Measures Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct security measures at entrances to Carl Schurz Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date:
July 2020
Procurement
Start Date: July 2020
Projected Completion Date:
March 2021
Completion
Date:
December 2022
Construction
Start Date: April 2023
Projected Completion Date:
April 2024
Completion Date: November 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Carl Schurz Park, Manhattan
York Avenue, Gracie Square, FDR Drive
Community Board: 08
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025