Carl Schurz Park Security Measures Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct security measures at entrances to Carl Schurz Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: December 2022

Construction

Start Date: April 2023
Projected Completion Date: April 2024
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $1,570,000
Funding Source: Mayoral

Location

Carl Schurz Park, Manhattan
York Avenue, Gracie Square, FDR Drive
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024