Cunningham Park Redwood Upper Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Redwood Upper Playground in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: June 2020

Procurement

Start Date: June 2020
Projected Completion Date: March 2021
Completion Date: April 2022

Construction

Start Date: October 2022
Projected Completion Date: October 2023
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $4,001,000
Funding Source: Mayoral

Location

Cunningham Park, Queens
193rd Street and Aberdeen Road and Radnor Road
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024