Cunningham Park Redwood Upper Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Redwood Upper Playground in Cunningham Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
April 2022
Construction
Start Date: October 2022
Projected Completion Date:
October 2023
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Cunningham Park, Queens
193rd Street and Aberdeen Road and Radnor Road
Community Board: 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024