Jamaica Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Jamaica Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2019
Projected Completion Date:
April 2020
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
January 2021
Completion
Date:
April 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jamaica Playground, Queens
110th Avenue between 160th Street and Union Hall Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower