Drew Playground Park Security Lighting Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct new park security lighting in Drew Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2018
Projected Completion Date:
January 2019
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
January 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Drew Playground, Bronx
Fulton Avenue between East 169th Street and East 170th Street
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project