Quarry Ballfields Synthetic Turf Field Construction
-
100% complete
-
100% complete
-
88% complete
This project will construct a synthetic turf soccer field and sitting area at Quarry Ballfields.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2019
Projected Completion Date:
May 2020
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2021
Completion
Date:
April 2024
Construction
Start Date: March 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Quarry Ballfields, Bronx
East 181st Street and Oak Tree Place between Quarry Road and Hughes Avenue
Community Board: 06
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024