Washington's Walk Strong Street Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    61% complete

This project will reconstruct Strong Street Playground in Washington's Walk.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: March 2024

Construction

Start Date: April 2024
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $3,040,000
Funding Sources:
  • Borough President
  • City Council

Location

Washington's Walk, Bronx
Strong Street and Reservoir Avenue
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 02/21/2025