Washington's Walk Strong Street Playground Reconstruction
-
100% complete
-
100% complete
-
54% complete
This project will reconstruct Strong Street Playground in Washington's Walk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
May 2022
Procurement
Start Date: May 2022
Projected Completion Date:
February 2023
Completion
Date:
March 2024
Construction
Start Date: April 2024
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Washington's Walk, Bronx
Strong Street and Reservoir Avenue
Community Board: 08
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024