Washington's Walk Strong Street Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    54% complete

This project will reconstruct Strong Street Playground in Washington's Walk.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: May 2022

Procurement

Start Date: May 2022
Projected Completion Date: February 2023
Completion Date: March 2024

Construction

Start Date: April 2024
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $3,040,000
Funding Sources:
  • Borough President
  • City Council

Location

Washington's Walk, Bronx
Strong Street and Reservoir Avenue
Community Board: 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024