Gerard P. Dugan Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, swings, spray shower, and seating area at Gerard P. Dugan Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $3,424,000
Funding Sources:
  • City Council
  • Mayoral

Location

Gerard P. Dugan Playground, Staten Island
Mill Road between Tysens Lane and Isernia Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project