Manhattan Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct synthetic turf fields at various locations in Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
May 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
March 2019
Construction
Start Date: April 2019
Projected Completion Date:
April 2020
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Baruch Playground, Manhattan
Stanton, Margin Streets & Baruch Place
Community Board: 03 -
De Witt Clinton Park, Manhattan
West 52 Street to West 54 Street, 11 Avenue to 12 Avenues
Community Board: 04 -
Frederick Douglass Playground, Manhattan
West 100-101 Street, Amsterdam Avenue
Community Board: 07
Project Staff
Project Liaison: Cristin Leoutsakos