Manhattan Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct synthetic turf fields at various locations in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,781,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025