Bridge Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Bridge Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $2,575,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Bridge Playground, Bronx
Boscobel Place, Undercliff Avenue, University Avenue
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024