Bridge Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Bridge Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
January 2020
Completion
Date:
January 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: April 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Bridge Playground, Bronx
Boscobel Place, Undercliff Avenue, University Avenue
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024