NYCHA Pomonok Houses Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new open space within the NYCHA Pomonok Houses.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: April 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $2,057,000
Funding Source: Mayoral

Location

Legacy Park, Queens
71st Avenue between Kissena Boulevard and Parsons Boulevard
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024