Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
February 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: November 2022