Woodside Houses Seating Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new seating area within the NYCHA Woodside Houses.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: February 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $898,000
Funding Source: Mayoral

Location

Woodside Houses Playground, Queens
Broadway and 49th Street
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024