Bronx Street Tree Planting FY19 - Community Boards 1-8

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 1-8 in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: August 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Completion Date: January 2019

Construction

Start Date: October 2018
Projected Completion Date: May 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $990,000
Funding Source: Mayoral