Bronx Street Tree Planting FY19 - Community Boards 1-8
-
100% complete
-
100% complete
-
100% complete
This project will plant street trees in Community Boards 1-8 in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
August 2018
Completion Date:
May 2018
Procurement
Start Date: May 2018
Projected Completion Date:
February 2019
Completion
Date:
January 2019
Construction
Start Date: October 2018
Projected Completion Date:
May 2019
Completion Date: January 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024