Queens Street Tree Planting FY19 - Community Boards 6,9,10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 6, 9, and 10 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: August 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Completion Date: January 2019

Construction

Start Date: October 2018
Projected Completion Date: May 2019
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $984,000
Funding Source: Mayoral

Location

Various locations in Queens