Brooklyn Street Tree Planting FY19 - Community Boards 11,13,15
-
100% complete
-
100% complete
-
100% complete
This project will plant street trees in Community Boards 11, 13, and 15 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
August 2018
Completion Date:
May 2018
Procurement
Start Date: May 2018
Projected Completion Date:
February 2019
Completion
Date:
January 2019
Construction
Start Date: September 2018
Projected Completion Date:
June 2019
Completion Date: May 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024