Grant Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    57% complete

This project will construct Grant Park, including converting the roadbed to recreational space.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: November 2020
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: September 2023

Construction

Start Date: October 2023
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $17,002,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Grant Park, Bronx
Grant Avenue between East 169th Street and East 170th Street
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024