Grant Park Construction
-
100% complete
-
100% complete
-
65% complete
This project will construct Grant Park, including converting the roadbed to recreational space.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
November 2020
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
September 2023
Construction
Start Date: October 2023
Projected Completion Date:
October 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Grant Park, Bronx
Grant Avenue between East 169th Street and East 170th Street
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project