Grant Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will construct Grant Park, including converting the roadbed to recreational space.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: November 2020
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: December 2021
Completion Date: September 2023

Construction

Start Date: October 2023
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $17,002,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Grant Park, Bronx
Grant Avenue between East 169th Street and East 170th Street
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025