Corporal Irwin Fischer Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct Corporal Irwin Fischer Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: November 2020
Completion Date: April 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: February 2023