Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY19

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in the Bronx and Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: August 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2021
Completion Date: February 2021