Bronx and Manhattan Tree-Damaged Sidewalk Reconstruction FY19
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in the Bronx and Manhattan.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
May 2018
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
August 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2021
Completion Date: February 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Various locations in the Bronx and Manhattan
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024