Brooklyn Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 7,10-13,15,18
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Brooklyn Community Boards 7, 10-13, 15, and 18.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
May 2018
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
August 2019
Construction
Start Date: September 2019
Projected Completion Date:
August 2021
Completion Date: April 2021