Brooklyn Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 7,10-13,15,18

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Brooklyn Community Boards 7, 10-13, 15, and 18.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: August 2021
Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $1,568,000
Funding Source: Mayoral

Location

Various locations, in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024