Randall's Island PEP Academy Complex Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the parking lot at the Randall's Island Parks Enforcement Patrol (PEP) Academy Complex.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
July 2018
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
April 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
Hell Gate Circle between Sunken Meadow Loop and Rivers Edge Road, under the Robert F. Kennedy Triborough Bridge
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024