Randall's Island PEP Academy Complex Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the parking lot at the Randall's Island Parks Enforcement Patrol (PEP) Academy Complex.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,351,000
Funding Source: Mayoral

Location

Randall's Island Park, Manhattan
Hell Gate Circle between Sunken Meadow Loop and Rivers Edge Road, under the Robert F. Kennedy Triborough Bridge