Morton Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Morton Playground, including the basketball courts, play equipment, safety surface, water and drainage systems, park lighting, and landscaping.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date:
September 2019
Procurement
Start Date: September 2019
Projected Completion Date:
June 2020
Completion
Date:
April 2021
Construction
Start Date: July 2021
Projected Completion Date:
July 2022
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Aqueduct Walk, Bronx
University Avenue and Morton Place
Community Board: 07
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project