Morton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Morton Playground, including the basketball courts, play equipment, safety surface, water and drainage systems, park lighting, and landscaping.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: April 2021

Construction

Start Date: July 2021
Projected Completion Date: July 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $4,918,000
Funding Source: Mayoral

Location

Aqueduct Walk, Bronx
University Avenue and Morton Place
Community Board: 07

 

Project Staff

Project Liaison: Katerine Borrome