Ridgewood Reservoir Invasive Species Removal
-
100% complete
-
100% complete
-
5% complete
This project will remove invasive species and plant new and replacement trees at Ridgewood Reservoir in Highland Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
December 2018
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
August 2022
Construction
Start Date: October 2022
Projected Completion Date:
October 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highland Park, Queens
Vermont Place, Highland Boulevard, Jackie Robinson Parkway, Cypress Hills Street
Community Board: 05, 05
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024