Ridgewood Reservoir Invasive Species Removal

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will remove invasive species and plant new and replacement trees at Ridgewood Reservoir in Highland Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: August 2022

Construction

Start Date: October 2022
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $3,250,000
Funding Source: Mayoral

Location

Highland Park, Queens
Vermont Place, Highland Boulevard, Jackie Robinson Parkway, Cypress Hills Street
Community Board: 05, 05

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024