Redfern Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Redfern Playground and the adjacent NYCHA open space.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
February 2021
Completion
Date:
November 2021
Construction
Start Date: February 2022
Projected Completion Date:
February 2023
Completion Date: February 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Redfern Playground, Queens
Redfern Avenue and Beach 12th Street
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project