Manhattan Beach Center Promenade Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the center portion of Manhattan Beach Promenade, around the bathhouse and entryways to the beach with new concrete pavement, drainage, seating, landscaping, steps, and ADA-compliant ramps.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
May 2019
Completion Date:
June 2019
Procurement
Start Date: June 2019
Projected Completion Date:
March 2020
Completion
Date:
June 2021
Construction
Start Date: June 2021
Projected Completion Date:
November 2022
Completion Date: December 2021
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Manhattan Beach Park, Brooklyn
Oriental Boulevard between Ocean Avenue and Mackenzie Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025