Highland Park Ridgewood Reservoir Gatehouse 27 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Gatehouse 27 next to Ridgewood Reservoir in Highland Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: September 2022

Construction

Start Date: February 2023
Projected Completion Date: August 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $5,300,000
Funding Source: Mayoral

Location

Highland Park, Queens
Jackie Robinson Parkway between Vermont Place and Cypress Hills Street
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024