Design
Assigned & Start Date: February 2021
Projected Completion Date:
May 2021
Completion Date:
October 2021
Procurement
Start Date: October 2021
Projected Completion Date:
July 2022
Completion
Date:
April 2024
Construction
Start Date: October 2024
Projected Completion Date:
October 2025
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Blood Root Valley, Staten Island
Rockland, Manor and Brielle Avenues, Forest Hill Road
Community Board: 02 -
Flushing Meadows Corona Park, Queens
Grand Central Parkway, Van Wyck Expressway
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024