Orchard Beach Nature Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Orchard Beach Nature Center in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2018
Projected Completion Date:
May 2019
Completion Date:
January 2021
Procurement
Start Date: January 2021
Projected Completion Date:
October 2021
Completion
Date:
February 2023
Construction
Start Date: May 2023
Projected Completion Date:
May 2024
Completion Date: May 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park, Bronx
North section of Orchard Beach Boardwalk
Community Board: 10, 12
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025