Staten Island Tree-Damaged Sidewalk Reconstruction FY19
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct sidewalks damaged by adjacent city-owned trees in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
May 2018
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
July 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2021
Completion Date: February 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Last updated: 11/22/2024