Queens Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 1-7,9,10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Queens Community Boards 1-7, 9, and 10.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: July 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2021
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $2,546,000