Brooklyn Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 1-6,8,9,14,16,17

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Brooklyn Community Boards 1-6, 8, 9, 14, 16, and 17.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2021
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $1,690,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024