Alley Pond Park Living Shoreline Construction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a living shoreline with oyster habitats along the western shore of Alley Creek at Alley Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: June 2020
Completion Date: November 2020

Construction

Start Date: February 2021
Projected Completion Date: August 2021
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $89,000
Funding Source: Federal

Location

Alley Pond Park, Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard
Community Board: 11

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024