Prall Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Prall Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Completion
Date:
February 2023
Construction
Start Date: May 2023
Projected Completion Date:
November 2024
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Prall Playground, Staten Island
Forest Avenue and Elizabeth Street
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024