Prall Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Prall Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: June 2021

Procurement

Start Date: June 2021
Projected Completion Date: March 2022
Completion Date: February 2023

Construction

Start Date: May 2023
Projected Completion Date: November 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $1,575,000
Funding Source: Mayoral

Location

Prall Playground, Staten Island
Forest Avenue and Elizabeth Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024