Bayside Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Bayside Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date:
July 2019
Procurement
Start Date: July 2019
Projected Completion Date:
April 2020
Completion
Date:
February 2022
Construction
Start Date: June 2022
Projected Completion Date:
December 2023
Completion Date: March 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Bayside Playground, Queens
Beach Channel Drive and Seaside Avenue
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025