Quisqueya Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
49% complete
This project will reconstruct the public restroom building in Quisqueya Playground in Highbridge Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Completion
Date:
February 2023
Construction
Start Date: April 2023
Projected Completion Date:
October 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highbridge Park, Manhattan
Amsterdam Avenue between West 179th Street and West 180th Street
Community Board: 10, 12
Project Staff
Project Liaison: Steve Simon