Cooper Park Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Cooper Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Completion
Date:
October 2022
Construction
Start Date: March 2023
Projected Completion Date:
September 2024
Completion Date: September 2024