Cooper Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Cooper Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: June 2021

Procurement

Start Date: June 2021
Projected Completion Date: March 2022
Completion Date: October 2022

Construction

Start Date: March 2023
Projected Completion Date: September 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $1,645,000
Funding Source: Mayoral

Location

Cooper Park, Brooklyn
Maspeth Avenue, Olive Street, Sharon Street, Morgan Avenue
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024