Grove Hill Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Grove Hill Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: March 2020

Construction

Start Date: October 2020
Projected Completion Date: April 2022
Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $1,551,000
Funding Source: Mayoral

Location

Grove Hill Playground, Bronx
East 158th Street between Eagle Avenue and Cauldwell Avenue
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025