Shore Front Parkway Amenities Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct park amenities, including sidewalks, seating, bike racks, fencing, game tables, drinking fountains, and landscaping along Shore Front Parkway.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: December 2020
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: April 2023

Construction

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $3,969,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Rockaway Beach Boardwalk, Queens
Shore Front Parkway between Beach 73rd Street and Beach 109th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024