Shore Park and Parkway Path and Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct a portion of the western Shore Road Park path and the pavement surrounding the Field House.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
June 2022
Construction
Start Date: July 2022
Projected Completion Date:
July 2023
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Shore Park and Parkway, Brooklyn
Shore Road Park between 95th and 99th Streets
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024