Shore Park and Parkway Path and Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a portion of the western Shore Road Park path and the pavement surrounding the Field House.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: June 2022

Construction

Start Date: July 2022
Projected Completion Date: July 2023
Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $1,270,000
Funding Source: Mayoral

Location

Shore Park and Parkway, Brooklyn
Shore Road Park between 95th and 99th Streets
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024