St. Mary's Park Ballfields and Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields and dog run, including natural turf, irrigation, sports lighting, fencing and landscaping at St. Mary's Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: November 2018

Construction

Start Date: December 2018
Projected Completion Date: March 2020
Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $8,965,000
Funding Source: Mayoral

Location

St. Mary's Park, Bronx
St. Mary's Street and Jackson Avenue
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024