Highbridge Anchor Park Reconstruction Phase I

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the staircase and pathways, including pavement, drainage, lighting and planting, in Highbridge Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: December 2018

Construction

Start Date: December 2018
Projected Completion Date: June 2020
Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $9,864,000
Funding Source: Mayoral

Location

Highbridge Park, Manhattan
West 181st Street to Dyckman Street
Community Board: 10, 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024