Astoria Park Charybdis Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Public Restroom Building at Charybdis Playground in Astoria Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: September 2019

Construction

Start Date: February 2020
Projected Completion Date: August 2021
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $1,435,000
Funding Source: Mayoral

Location

Astoria Park, Queens
Between Shore Boulevard and 19th Street at 23rd Road
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024