Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Brooklyn War Memorial Restroom and Eleanor Roosevelt Playground public restroom building.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2017
Projected Completion Date: November 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: May 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2023
Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $1,697,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024