Marlboro Playground and Cadman Plaza Park Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the public restroom buildings at Marlboro Playground and Cadman Plaza Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2017
Projected Completion Date: August 2019
Completion Date: January 2023

Procurement

Start Date: January 2023
Projected Completion Date: September 2021
Adjusted Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • Mayoral
  • State

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024