Forest Park Garage and Oak Ridge Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofs at Forest Park Garage and Oak Ridge in Forest Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: July 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2021
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $2,013,000
Funding Source: Mayoral

Location

Forest Park, Queens
Myrtle Avenue, Union Turnpike, Park Lane South
Community Board: 05, 05, 06, 09

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024