Beach 108th Street Esplanade Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Beach 108th Street Esplanade.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2019
Projected Completion Date:
September 2020
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
July 2022
Construction
Start Date: September 2022
Projected Completion Date:
September 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Federal
Location
Park at Beach 108 Street, Queens
Beach Channel Drive between Beach 108th Street and Rockaway Freeway
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025