Hudson and West Houston Streets Plaza Construction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a new open space at Hudson Street and West Houston Street.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Assigned & Start Date: January 2024
Projected Completion Date: January 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • Mayoral

Location

Hudson Street and West Houston Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024