Hudson and West Houston Streets Plaza Construction
-
100% complete
-
0% complete
-
0% complete
This project will construct a new open space at Hudson Street and West Houston Street.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: January 2024
Projected Completion Date:
January 2025
Completion Date:
February 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Hudson Street and West Houston Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 02/21/2025